1 Status Timeline #

The status timeline appears at the top of each Fire Compliance detail screen. It shows a visual summary of the record’s progress through the following stages:

  • Inspection Identified – the initial status when a record is created.
  • Inspection Requested – after Send Inspection Request is clicked.
  • Inspection Date Confirmed – after the inspection date and time are saved.
  • Inspection Scheduled and Informed – after the inspection schedule is confirmed and communicated.
  • Inspection Schedule – after the inspection schedule is set.
  • Inspection Report Reminder – after an inspection report reminder is sent.
  • Inspection Completed – after Mark Inspection Complete is clicked.
  • Inspection Report Uploaded – after the inspection report is uploaded.
  • Awaiting Works Approval – after inspection is complete and works approval is pending.
  • Remediation in Progress – after remediation works have commenced.
  • Repairs Completed – after all remediation works are completed.
  • AFSS Submitted – after the final signed AFSS document is uploaded.
  • Completed – after all requirements for the compliance record are finalised.
  • Extension Requested – after an extension request has been submitted.

Completed stages are shown in green colour. Pending stages are greyed out.

[SCREENSHOT: Status timeline showing completed and pending stages]

2 Detailed Activity Log #

Below the status timeline, the detailed activity log provides a full audit trail of everything that has happened on the record, including:

  • Date and time of each action
  • User who performed the action
  • Description of what was done (e.g., Contractor assigned, Status changed from Inspection Identified to Inspection Requested)